Der er bl.a. følgende krav for at blive prækvalificeret:

The applicant must meet all the minimum requirements below:

Regarding train solution

1) The applicant has delivered an electric mainline regional and/or fast passenger train solution with (a) AC or multi-system (combination of AC/DC), (b) track width 1435 mm, (c) operational speed of min. 160 km/h and (d) a 25 kV 50 Hz voltage system.

2) The applicant has delivered an electric mainline regional and/or fast passenger train solution with (a) AC or multi-system (combination of AC/DC), (b) track width 1435 mm and (c) operational speed of min. 200 km/h.

3) The applicant has delivered an electric mainline regional and/or fast passenger train solution with (a) AC or multi-system (combination of AC/DC), (b) track width 1435 mm, (c) operational speed of min. 160 km/h and (d) low floor that allows level access from 550 mm platforms.

4) The applicant has delivered an electric mainline regional and/or fast passenger train solution with (a) AC or multi-system (combination of AC/DC), (b) track width 1435 mm, (c) operational speed of minimum 160 km/h and (d) multiple operation of minimum 3 trainsets.

Deliveries in minimum requirement 1) - 4) shall have been made within the past 5 years prior to the deadline for submission of application for prequalification. By “delivered” in minimum requirement 1) - 4) and section III.1.3), 1st para., is understood when a train is under production for or taken over and put in commercial service by an external customer.

--